Examining opportunities to improve the pre-construction schedule performance of Seattle Public Utilities scope in Seattle Department of Transportation capital projects

dc.contributor.advisorWhittington, Janice
dc.contributor.advisorHerranz, Joaquín
dc.contributor.authorHerrera, Marlon Dylan
dc.date.accessioned2018-11-28T03:22:02Z
dc.date.available2018-11-28T03:22:02Z
dc.date.issued2018-11-28
dc.date.submitted2018
dc.descriptionThesis (Master's)--University of Washington, 2018
dc.description.abstractThis study discerns and analyzes opportunities to improve the schedule performance of the City of Seattle’s water, sewer, and drainage improvements that are delivered through transportation capital projects. This issue is particularly salient, as Seattle’s water, sewer, and garbage ratepayers are spending over $100 million each year on capital improvements that are a result of unprecedented transportation construction – which inevitably creates impacts and opportunities to below-grade infrastructure. This research takes the form of a multi-case descriptive study, examining three projects with significant utility scope that was delivered through transportation contracts. Specifically, this thesis focuses on schedule performance during the initiation, options analysis, and design phases of the project delivery lifecycle. As a result, this research found misaligned production systems between the utility and transportation agencies, as well as divergent policy drivers and mental models that reinforce the status quo. These findings and the following recommendation are derived from semi-structured interviews with project team members, observation of project delivery processes and artifacts, and pertinent theories, empirics, and literatures of practice. A recommendation to implement lean production – or a continuous improvement culture based on front-line empowerment and eliminating waste – is put forward from a limited policy analysis.
dc.embargo.termsOpen Access
dc.format.mimetypeapplication/pdf
dc.identifier.otherHerrera_washington_0250O_18558.pdf
dc.identifier.urihttp://hdl.handle.net/1773/43166
dc.language.isoen_US
dc.rightsCC BY
dc.subjectcapital project
dc.subjectintergovernmental
dc.subjectProject delivery
dc.subjecttransportation
dc.subjectwastewater
dc.subjectwater
dc.subjectPublic administration
dc.subjectManagement
dc.subjectUrban planning
dc.subject.otherUrban planning
dc.titleExamining opportunities to improve the pre-construction schedule performance of Seattle Public Utilities scope in Seattle Department of Transportation capital projects
dc.typeThesis

Files

Original bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
Herrera_washington_0250O_18558.pdf
Size:
1.14 MB
Format:
Adobe Portable Document Format

Collections